Job Budget Analysis
In the job budget analysis is there a way to manually adjust the figures in ther Adjusted Budget. Does this pull any figures from Open Purchase orders?
- 5 years ago
Hi Kristyh1
The Adjusted Budget value listed on the Job Budget Analysis report is a calculated value from the enter budget value and the entered percentage complete of that job. This is not a value that a user can update when running the report, you do need to update either the Budget of the job or the percentage complete of that job to update those values.
In terms of orders, no accounts are impacted by orders consequently no jobs values are impacted as well.